BOE Watch · Published on 27 November 2026
The Official State Gazette of 27 November 2026 is dominated by energy. Neighbours who share a solar installation get simpler rules from 28 November. Renewable energy communities finally have detailed rules on who can join and where. Gas bills will have to show more information, and employers face stricter conditions for the official equality label.
Key facts
- Shared solar. From 28 November, a change to the sharing agreement only needs the signatures of the people who join, leave or change their share. The minimum stay in a self-consumption modality falls to one month.
- Energy communities. Members must own property, live, have their registered office or hold a supply point near the project. The test depends on the size of the municipality.
- Gas bills. Bills must carry a link and QR code to the CNMC comparator for gas and electricity offers, and information on how much of the gas comes from renewable sources.
- Employers. The «Igualdad en la Empresa» label is renamed and tightened. Current holders keep it and have one year to meet the new requirements.
On this page
Shared solar: simpler rules for neighbours from 28 November
Royal Decree 1063/2026 of 26 November amends Royal Decree 244/2019, the main regulation on electricity self-consumption. It comes into force on 28 November 2026. It matters most to owners in blocks of flats and to neighbours who share one solar installation, which the rules call collective self-consumption.
- Changing the sharing agreement. Until now every participant had to sign any change. A partial change, including a neighbour joining or leaving, now only needs the signatures of those who join, leave or change their share. The others’ existing signatures remain valid, and they must be formally told of the change within five working days.
- Replacing a participant. When a new consumer takes over a departing consumer’s share unchanged, only the newcomer signs. The departing holder must agree, unless the departure follows the end of their supply contract, their death or a change in the holder of the supply point. Until someone takes the share, its energy counts as surplus.
- One-month minimum stay. The minimum time in the chosen modality falls from four months to one month, and the same period applies to changes in the sharing coefficients.
- A self-consumption manager. The participants may appoint one person or company to deal with the distributor and suppliers on their behalf. The manager does not have to be a participant, but the appointment needs the agreement of all of them.
- Faster start-up and meters. The distributor can register the scheme once it receives the documents from at least one participant or from the manager. If the generation meter is rented from the distributor, it must be installed within one month. Participants keep their existing consumption meters.
- Data and bills. Participants can see the installation’s generation data on the same platforms where they check their consumption. Within one month, the model electricity bill must be amended so that it shows the shared installation’s code, the net generation and the energy allocated to each participant.
The decree also creates a new «shared surplus» modality. One principal consumer has the installation connected to their own supply, uses the energy first and shares only the surplus with the other participants. It also allows an individual installation without surplus to be combined with any other modality.
Home batteries are treated as if they were a generating installation, and the electricity they draw is exempt from network tolls and system charges. That provision only takes effect when the Government adopts the further regulation the decree announces, so nothing changes for battery owners yet.
Energy communities: who can join and where
Royal Decree 1065/2026 of 26 November sets out the rules for renewable energy communities and citizen energy communities. These are legal entities controlled by individuals, small businesses or local authorities, whose main purpose is to give their members or the local area environmental, economic or social benefits rather than financial profit. The decree comes into force on 28 November 2026.
- Proximity. In a municipality of up to 50,000 inhabitants, members must own property, live, have their registered office or hold a supply point in that municipality or in adjoining ones, with a combined population of no more than 50,000 and within 25 km of the project. Between 50,000 and 250,000 inhabitants, the link must be with the same municipality. Above 250,000, it must be within 5 km of the project.
- Households keep their rights. Consumers, including households, can join while keeping all their rights as electricity consumers. Members may leave at any time, subject to the notice rules in the statutes, which may also allow them to recover what they invested.
- Communities across regions. A community that spans more than one autonomous community needs at least five members, and no single member may hold more than 40% of the votes or the ownership. It must file a responsible declaration with the Directorate General for Energy Policy and Mines. Communities already operating have six months to file it.
- Grid capacity. At transmission nodes reserved for a capacity tender, 10% of the reserved capacity is released for new generation owned by renewable energy communities. This applies for two years.
Gas bills and longer notice periods for power line projects
Royal Decree 1062/2026 of 26 November is mainly about grid access for renewable projects, but two changes reach ordinary consumers and landowners. It comes into force on 28 November 2026.
- Gas bills. Bills must show a link and QR code to the CNMC comparator for both gas and electricity offers. The personalised consumption data in that link becomes mandatory three months after the CNMC publishes the technical format in the BOE.
- Renewable gas. Bills must eventually show the origin and environmental impact of the gas supplied. In the meantime, within three months, suppliers must print a line in 12-point bold stating the percentage of renewable gas, backed by guarantees of origin, that they supplied to all their customers the previous year.
- Public utility declarations. When a power line or other electricity installation needs land through expropriation or a right of way, the public consultation period rises from 30 to 45 days. Distribution lines below 36 kV keep 30 days. Notices must also appear on the electronic office of the Government Delegations and in at least two widely read media.
Employers: a stricter equality label
Royal Decree 1042/2026 of 25 November replaces the rules on the «Igualdad en la Empresa» label, which becomes «Igualdad en la empresa y por una sociedad libre de violencia de género». Any company or entity operating in Spain may apply, except public administrations. The decree comes into force on 28 November 2026 and repeals Royal Decree 1615/2009.
- Clean record. No final penalty for a serious or very serious equality infringement in the previous three years, and no very serious penalty under immigration law in the same period. Tax and Social Security payments must be up to date.
- Harassment and training. A specific procedure against sexual harassment that expressly covers digital harassment, and training on sexual violence at work offered to the whole workforce, managers included, in one of the last two years.
- Pay and equality plans. An up-to-date pay register for every applicant. Companies that must have an equality plan also need a registered plan at least two years old, or one that is not their first, an evaluation report and a job evaluation.
- Current holders. Companies that already hold the label keep it indefinitely under the new name, with one year to adapt to the new requirements.
Also in the gazette
- Foster carers. Royal Decree 1035/2026 lets specialised full-time foster carers who receive compensation join the General Social Security Scheme through a special agreement. It covers retirement, permanent incapacity, and death and survivors’ benefits from non-occupational causes. An application made within 90 days of the fostering decision takes effect from the start of the placement. The decree comes into force six months after its publication.
- Monzo and Social Security. The General Treasury of the Social Security authorises the Spanish branch of Monzo Bank Europe to act as a collaborating entity for collecting Social Security resources and paying its obligations, with effect from 1 December 2026.
- Pet insurance. Order ECM/1274/2026 authorises AXA Seguros Generales to transfer all its SantéVet pet health policies, sold through the French intermediary Vetassur, to AXA France IARD. Each policyholder must be notified individually and may cancel the policy within one month of 27 November 2026, with a refund of the unused premium.
- Refrigerant gases. Royal Decree 1066/2026 regulates the marketing and use of fluorinated greenhouse gases, natural refrigerants and the equipment that contains them, and the training of the professionals who handle them.